Sri Lanka Electricity Act 2024 · As enacted · Part IV · Establishment of the National System Operator
10. Issue of licence to the National System Operator,the Board of Directors and functions
Official English translation. The Sinhala text prevails. Open the official Sinhala text, official PDF on documents.gov.lk
Official translationFrom Department of Government Printing, unchanged
A Company referred to in section 9 shall be the “National System Operator” (hereinafter referred to as the “National System Operator”) and a national system operator licence shall be issued to such company by the
Regulator.
The administration and management of the affairs of the National System Operator shall be vested in a Board of Directors appointed by the Minister which shall consist of –
a representative from the Ministry of the Minister holding a position not less than an additional secretary;
a Deputy Secretary to the Treasury;
an electrical engineer who has at least fifteen years of experience in power system operation and planning;
a person who has at least fifteen years of experience in project finance and procurement;
and
a person who has expertise, reached eminence and has at least fifteen years of experience in commercial law, and one of whom shall be appointed as the Chairperson by the Minister.
The Chief Executive Officer of the National System
Operator shall be a person who has expertise, reached eminence and has at least twenty years of experience in electrical engineering and administration who shall be appointed by the Board with the approval of the Minister.
The Board of Directors and the Chief Executive
Officer of the National System Operator shall submit to the
Minister, a general disclosure of their interests as at the date of their appointment before assuming office as a Director of the Board of Directors or the Chief Executive Officer, as the case may be.
Any Director or the Chief Executive Officer who is directly or indirectly interested in any matter that is to be taken up before the Board shall disclose the nature of such interest to the Board and shall not take part in any deliberation or decision of the Board with regard to that matter.
The National System Operator shall be responsible for–
operating and maintaining the System Control
Centre for the real time operation of the power system of Sri Lanka;
submitting the annual power procurement plan based on the least economic cost on or before the thirtieth day of September of every year to the
Regulator setting out the manner in which the
National System Operator intends to meet the projected demand for the succeeding year for electricity from the available generation capacity including new generation capacity expected to be commissioned in the succeeding year;
ensuring that the integrated operation of the power system of the country be based on the projections in the annual power procurement plan, and the monitoring and reporting at the end of every calendar month, of any variations from the annual power procurement plan to the Regulator with reasons therefor;
the coordinated operation of the power system to ensure in real time the balance between electricity supply and demand and for this purpose, shall ensure-
compliance with principles, guidelines and methodologies in respect of optimal generation scheduling and dispatch, as shall be prescribed;
optimal generation scheduling and dispatch of electricity from the generating plants in accordance with the power purchase agreements or standardized power purchase agreements which have been entered into or have been transferred to the National
System Operator, on the most economical and advantageous terms and in a transparent and accountable manner to meet the total demand for electricity at any given time. The procedures to be followed and the formats of the agreements to be used shall be as prescribed;
carrying out real time operations for grid control and daily power dispatch through the secure and economic operation of the
National Grid of Sri Lanka in accordance with the grid code, monitor the grid operations and provide the information and data required for conducting the dispatch audit to the Regulator in such manner, as shall be prescribed;
ensuring the non-discriminatory transmission congestion management in a timely and effective manner;
the establishment of a bulk supply transactions account and monthly public disclosure of the details of such account to record all financial transactions relating to the purchase of bulk electricity from a generation licensee through power purchase agreements or standardized power purchase agreements and selling to the distribution licensees through power sales agreements, or with the prior approval of the
Regulator to any other consumers, or in the case of electricity trading with the regional market, including monitoring the import and export of electricity. The procedures to be followed and the formats of the bulk supply transactions account and the agreements to be used shall be as prescribed;
maintaining records of the quantity and quality of electricity, transmitted through the National
Grid of Sri Lanka;
exercising supervision and control over the overall operation of the National Grid of Sri Lanka; and
subject to the provisions of section 11, procuring energy storage and ancillary services as determined, from time to time, to manage the intermittent nature of output from renewable energy plants, in accordance with the procedures approved by the Regulator:
Provided that, the National System Operator shall not engage in any commercial activity other than in the manner and subject to such conditions, as shall be prescribed.
The Minister shall prescribe the procedure, format and manner in which the matters specified in subsection (2)
are to be implemented by the National System Operator.
For the avoidance of doubt, it is hereby stated that, from and after the appointed date the transfer of functions of the Ceylon Electricity Board as specified in section 18
connected with -
generation scheduling, commitment, and merit order economic dispatch of generating plants;
optimised planning of future power system to meet the electricity demand taking into consideration cost, economic value and decarbonisation objects;
operation and maintenance of the System Control
Centre; and
procurement of electricity in bulk form, from the generation licensees and sale of such procured electricity in bulk form to distribution licensees and to any other consumers trading in the domestic, regional or international market, shall be done consequent to the vesting of the aforesaid functions of the Ceylon Electricity Board in the National
System Operator.
The National System Operator shall, in every two years prepare the Long Term Power System Development
Plan which shall include both generation and transmission capacity, energy storage and ancillary service additions covering a period of ten years and an indicative plan for further period of ten years in accordance with the approved national electricity policy and policy guidelines issued in terms of section 4.
The National System Operator shall, in preparing the said Long Term Power System Development Plan, take into consideration, the principle of least economic cost, the availability of the most economically advantageous electricity generation capacity and other feasible alternative scenarios and submit the same to the Regulator.
The Regulator shall, after consultation with the relevant stakeholders including the licensees, provide recommendations to the National System Operator within two months of receipt of the Plan.
The National System Operator shall finalise the plan taking into consideration, the recommendations received under paragraph (a) and submit the same to the
Minister within one month of receipt of such recommendations including the reasons for not accepting any recommendation made by the Regulator. The Minister shall, in consultation with the Regulator and the Council, review the plan and having satisfied with its consistency of the national electricity policy, submit the same to the
Cabinet of Ministers before the end of the year for approval.
The Cabinet of Ministers shall, having stated the reasons, either approve or disapprove the plan within three months of receipt of the Plan.
The National System Operator shall be held accountable for the implementation of the approved Long
Term Power System Development Plan.
The Minister and the Regulator shall forthwith be notified of any deviations made by the National System
Operator from the approved Plan.
The National System Operator shall annually forward a Report specifying the deviations made from the
Long Term Power System Development Plan and the reasons for such deviations and the economic considerations if any, which arise out of such deviations, to the Minister and the
Regulator.
The Long Term Power System Development Plan shall –
include plans to ensure that there is sufficient capacity from generation plants to meet the reasonable estimated demand for electricity, for both generation expansion and transmission network development, inclusive of evaluation of least economic cost generation technologies, energy conversion and storage technologies, and other demand side technologies;
identify the power generation capacity additions needed to meet the expected demand for electricity based on the priorities outlined in the national electricity policy;
identify new transmission capacity and transmission assets to augment the National Grid of Sri Lanka specified in section 15 and to provide connectivity to new power plants or to provide connectivity to the regional markets in accordance with the approved Long Term Power Development
Plan subject to such terms and conditions as approved by the Regulator.
The National System Operator shall be required to enter into transmission service agreements with the
National Transmission Network Service Provider and persons who are issued with additional transmission licences in terms subsection (2) of section 14 granting the National
System Operator with operating authority over transmission and network facilities owned by the National Transmission
Network Service Provider and additional transmission licensees.
The National System Operator shall have the exclusive right of trading electricity with other countries under the authority of a National System Operator licence issued under this Act.
The terms and conditions of trading which is intended to be done under paragraph (a) shall be approved by the Cabinet of Ministers.
No generation licensee shall be authorised to directly sell electricity to any country and no consumer or distribution licensee shall be authorised to purchase electricity from any country.
The National System Operator shall enter into–
power purchase agreements with generation licensees and transmission service agreements with transmission licensees as specified in subsection (12):
Provided that, all power purchase agreements and standardized power purchase agreements which had been entered into by the
Ceylon Electricity Board, and which are valid and are in operation on the day immediately preceding the appointed date shall be assigned to the National System Operator under the same terms and conditions for the remaining period of such power purchase agreements or standardized power purchase agreements and continue to be valid and effective as if entered into in terms of this Act. The generation licensees with whom such power purchase agreements and standardized power purchase agreements have been entered into shall be obliged to sell electricity to the
National System Operator until the expiration of such agreements;
power purchase agreements with generation licensees incorporated under the preliminary transfer plan specified in paragraph (a) of subsection (2) of section 18;
power sales agreements with distribution licensees incorporated under the preliminary transfer plan specified in paragraph (a) of subsection (2) of section 18;
a transmission service agreement with the
National Transmission Network Service Provider incorporated under the preliminary transfer plan specified in paragraph (a) of subsection (2) of section 18 and subsection (12) of this section.
Part V
National Transmission Network Service Provider
Part VI
Incorporation of Limited Companies Under the Companies Act…
Part VII
Licensing
Part VIII
Tariffs
Part IX
Wholesale Electricity Market
Part X
Consumer Protection
Part XI
Finance
Part XII
Miscellaneous
Part XIII
General
Part XIV