Sri Lanka Sustainable Energy Authority Act 2007 · As enacted · Part V · On-Grid and Off-Grid Renewable Energy Projects
16. On-grid renewable energy projects
Feedback & supportOfficial English translation. The Sinhala text prevails. Open the official Sinhala text, official PDF on documents.gov.lk
Notwithstanding the provisions in any other law to the contrary and subject to the provisions of section 71, no person shall engage in or carry on an on-grid renewable energy project for the generation and supply of power within a
on-grid renewable energy project
“on-grid renewable energy project” means an installation which converts any form of renewable energy to electricity and feeds electricity thus generated to the national electricity grid operated by Ceylon Electricity Board and which is carried on within any Development Area;
Development Area, except under the authority of a permit issued in that behalf by the Authority.
A person who is desirous of engaging in and carrying on an on-grid renewable energy project within a Development
Area, shall make an application to the Director-General for the same in the prescribed form together with the prescribed fee and the following documents :—
a copy of a map of the geographical location of the proposed project;
a brief description of the project, including the amount of power to be generated;
the total estimated cost and financial model, including optimization criteria adopted;
proof of availability of adequate finances or the manner in which the required finances for the project are to be obtained;
project location i. e. Weir and Power House relative to river or stream system if it is a Hydro Power project,
Wind Turbine and Structures if it is a Wind power project, Energy Plantation, Power House and Water
Source if it is a Biomass Project and Conversion
Facility relative to energy resource, if it is any other project ; and
a statement explaining how the applicant intends to evacuate electricity generated and the point at which the generator will be connected to the national grid and the geographical area traversed by the power line constructed for this purpose.
On receipt of an application under subsection (2), the
Director-General shall forthwith register such application along with the documents in a register maintained for that purpose, and issue a registration number to the applicant.