Part V · On-Grid and Off-Grid Renewable Energy Projects

17. Provisional approval to be granted

Official English translation. The Sinhala text prevails. Open the official Sinhala text, official PDF on documents.gov.lk

(1)

The Director-General shall after carrying out such preliminary screening of the proposed project as he considers necessary and in consultation with the Ceylon Electricity

Board, submit the registered application together with his observations on the proposed project, to the Committee for its approval.

(2)

The Committee shall where it considers it appropriate :—

(a)

grant provisional approval for the project which shall be communicated forthwith by the Director-General

Sri Lanka Sustainable Energy Authority to the applicant in the prescribed form, with a request to submit such documents and other information as shall be prescribed for the purpose, within six months of such communication being received by the applicant; or

(b)

refuse to grant provisional approval for the project which shall be communicated forthwith by the

Director-General to the applicant, stating the reasons for such refusal.

(3)

An extension of the period given for the submission of documents and information under paragraph (a) of subsection (1) may be granted by the Director-General where requested for, upto a maximum of another six months period.

(4)

A provisional approval granted under paragraph (a) of subsection (1) shall be valid for a period of one year from the date on which such approval is granted and shall stand cancelled automatically, if the documents and other information requested for is not submitted prior to the expiry of the period of one year.

Part VI

Acquisition and Leasing of Immovable Property for Projects

Part VII

Energy Efficiency and Conservation Programmes

Part VIII

Finance

Part IX

Staff of the Authority

Part X

General

Schedules