Schedule I to the principal enactment is hereby amended as follows: -
by the repeal of item (a) of that Schedule and the substitution therefor, of the following item: -
“(a) one company (hereinafter referred to as the “Generation Company”) of which one hundred per centum of the shares are held by the Secretary to the Treasury to take over the assets, liabilities and functions of the Ceylon Electricity
Board, as referred to in the preliminary transfer plan, relating to –
the hydropower generation;
Norochcholei
Lakvijaya
Coal
Power
Plant and
Lanka Coal Company (Pvt)
Limited;
the thermal power generation other than coal power generation;
the Mannar Thambapavani
Wind Power Plant; and
Trincomalee
Power
Company Limited;”;
by the repeal of items (b), (c) and (d) of that
Schedule;
by the repeal of item (e) of that Schedule and the substitution therefor, of the following item: -
Act, No. 14 of 2025
“(e) one company of which one hundred per centum of the shares are held by the
Secretary to the Treasury to take over the assets, liabilities and functions of the
Ceylon Electricity Board, as referred to in the preliminary transfer plan, relating to –
the development, maintenance and operation of the physical infrastructure that makes up the
National Grid of Sri Lanka;
other selected assets, functions and activities; and
LTL Holdings Limited and Sri
Lanka Energies (Pvt) Limited;”;
by the repeal of item (g) of that Schedule and the substitution therefor, of the following item: -
“(g) one company (hereinafter referred to as the “Distribution Company”) of which one hundred per centum of the shares are held by the Secretary to the Treasury to take over the assets, liabilities and functions of the Ceylon Electricity
Board, as referred to in the preliminary transfer plan, relating to –
the distribution divisions namely Division 1, Division 2,
Division 3 and Division 4;
Act, No. 14 of 2025
other selected assets, functions and activities; and
Lanka
Electricity
Company
(Pvt) Limited;”;
by the addition immediately after item (h) of that
Schedule, of the following new item: -
“(i) (i) such number of companies to take over the generation functions of the
Generation Company as referred to in the final transfer plan;
such number of companies to take over the distribution functions of the distribution divisions of the
Distribution Company as referred to in the final transfer plan.”.